Brent
Willey, Nilu Puri Basnyat, Ram Charitra Sah
Our
three member research team is in the process of
gathering information by reviewing project documents
and interviewing project and government officials,
donor representatives and project affected people
paying particular attention to what Melamchi Water
Supply Project (MWSP) will mean to the poor in the
Kathmandu Valley.
In general, MWSP is a major, multi-faceted water
supply project aimed at improving service and delivery
of water to the Kathmandu Valley. The four major
components of the MWSP are:
·
Infrastructure Development of the Water and Wastewater
System
· Social and Environmental Issues
· Institutional Reforms
· Organizational Structure for Project Implementation
Updated
Summary of Project
1)
Recent Update of Infrastructure Components
a)
Melamchi Diversion Scheme (MDS): Comprises a 18
km main access road (MAR), 4 adit access roads (AAR)
25 km total length, upgrading of a 22 km approach
road (UAR), a diversion weir, a desanding basin
at the intake, a two part 26.5 km tunnel, Power
Transmission Line (PTL) and substation.
Progress
Status: Pace of construction activities of the MAR
has increased, 75% completed. Temporary access North
of Chanaute is built. Blasting issues remain a security
concern and is hindering progress in a certain section.
The AAR work resumed in November but the progress
is very slow. Conflict with contractor, Hanil Koneko,
brought a halt to the progress altogether from February
17 to March 25, 2002. The UAR bid evaluation is
ongoing. The redesign of the road is resulting in
substantial changes in work volume. The technical
bid evaluation for the PTL was submitted to ADB
for approval. The notice for land acquisition was
published. The technical proposal for the Melamchi
Diversion Tunnel was evaluated and is under consideration
by the Board. The PQ evaluation of the construction
contractors was submitted to the Board.
b)
A Water Treatment Plant (WTP): Situated at Mahankal
near Sundarijal with an initial capacity of either
85 MLD or 170 MLD but could be expanded to 510 MLD
in the future.
Progress
Status: The design and bid document preparation
phase is completed. The consultants have been demobilized
and further work has been deferred for the time
being. The tender award date, however, is delayed
due to the different controversial design options
presented in SAPI II Report, land acquisition issues,
and a clause that suggests that the tender will
only be awarded after the management contractor
is selected. The start of the construction is currently
scheduled for 2006, and is dependent on the commencement
and completion dates of the tunnel Contracts.
c)
Bulk Distribution System (BDS): Bulk transmission
mains to transfer water to a yet undetermined number
of reservoirs.
Progress
Status: The supervision consultant recruitment process
has been deferred due to controversial findings
presented in the SAPI studies, land acquisition
issues, and a clause that suggests that the tender
will only be awarded after the Kathmandu Valley
Water Authority has been set in place.
d)
Wastewater System Improvements (WSI): Planned rehabilitation
of existing sewer networks and wastewater treatment
plants.
Progress
Status: The short-listing of applications from consulting
firms for the design and construction supervision
of WSI was completed in the last FY 2001/2002, and
has been evaluated. Both the short-listing and RFP
are waiting for the Board's approval. This work
has been considered to be of lesser priority in
comparison to the other critical activities of the
project. It has been jointly decided by HMG/N and
the donors to defer WSI activities until the DNI
strategy is finalized.
e)
Distribution Networks Improvements (DNI):
The
SAPI II study indicates the improvement works have
to be implemented in stages. And in the zoning plans
proposed under SAPI II, the distribution systems
within the municipalities of Kathmandu and Lalitpur
will be divided into 5 large distribution zones
by major rivers and municipal boundaries. Each of
these large zones will then be further divided into
a number of medium distribution zones.
The
spatial priority of DNI is also recommended under
SAPI II, which is based on existing water supply
conditions in that a higher priority has been given
to areas where existing supply conditions are less
favorable, except for the first priority area. SAPI
study selected the area to be supplied from the
Min Bhawan elevated tank as being the first priority
area for DNI. This area includes 'Area 1a' and 'Area
1b' proposed for implementation of the Manohara
Demonstration Scheme, and lies in Zone III.
Design
Concept: It is proposed that water from the Bansbari
and Mahankalchaur reservoirs should be distributed
through a Skeletal Distribution System (SDS). The
SDS has been configured through a hydraulic analysis
so that there will be a minimum head of 20 m at
every location along side the Ring Main. The distribution
system after SDS comprises of the primary, secondary
and tertiary distribution mains. It is therefore
necessary to keep the total head loss in these distribution
mains to be smaller than 10m so that there will
be a minimum remaining effective head of 10 m at
the ends of tertiary distribution mains.
Progress
Status: As part of the supplementary activities,
JBIC undertook Special Assistance for the Project
Implementation (SAPI) study to formulate basic strategies
for DNI. A water use survey was conducted by NGO
Forum for SAPI Phase II Study and the results indicated
the average domestic water demand under intermittent
supply was 80 lpcd and about 112 lpcd for 24 hour
supply. Based on these results a clearer development
strategy for the DNI/BDS implementation has emerged.
The
total cost of the BDS was reduced to 33.1 m US$
from the previous BDS estimate of 43.5 m US$ with
two service reservoirs of total capacity 40,000
cu. m and a smaller diameter transmission main of
1200mm. The cost of the Skeletal Distribution System
(SDS) is 21.6 m US$ and the DNI for 6 priority areas
was estimated at 101 m US$. The total cost thus
comes to 155.7 m US$ for BDS, SDS, DNI. The HMGN,
donors and MWSDB have yet to decide on the recommendations
of the SAPI Phase II report.
After
the World Bank withdrawal from its previous funding
commitments the new funding sources for the DNI
are yet to be finalized. However, ADB and JBIC have
indicated that they will facilitate to resolves
the funding issues.
2)
Recent Update on Institutional Reforms
Until
recently, the NWSC has been engaged in investment
planning, regulation and operation and hence also
not been able to perform all the responsibilities
as per the expectation. This needs splitting of
its role and responsibilities through the proposed
reform. All these three responsibility are proposed
to separately and autonomously perform by the creation
of three additional institutions. The civil society
role is felt important to make sure reliable water
supply in the valley through its constructive critical
support. A short-term international experience in
managing water supply will be augmented for the
improvement of the newly created institution responsible
for the water supply and wastewater management through
a financially binding performance based management
contract (MC).
The new institutional reform includes creation of
Water Authority (WA), Water Utility Operator (WUO)
and National Water Supply Regulatory Board (NWSRB)
as shown in figure given below.
WA owns the assets and responsible for investment
planning and water supply development, licensing,
policy and performance reporting. WA is governed
by a board including representatives of HMGN, the
5 municipalities in Kathmandu Valley, the 3 district
development committees in Kathmandu Valley, professional
associations, the business community, and civil
society.
WUO will be established as a limited liability company
under the provision of the Company Act 1997, responsible
to provide water and wastewater service in Kathmandu
valley accordance with license provision given by
WA. The four shareholders of the WUO Company include
HMGN, municipalities, civil society, and a trust
representing the interest of employees.
National Water Supply Regulatory Board (NWSRB) will
monitor MC and WUO and fix water tariff.
3) Recent Update on Project Finance and
Tariff Reforms
Costs
The
initial project funded cost for the Melamchi Water
Supply Project is $464 million while the most recent
adjusted cost estimate is $478 million. The increase
is largely due to additional security issues at
the site, approximately $8.3 million, which will
have to be funded by HMG/Nepal. Revised project
cost estimates could increase due to international
market cost, inflation, change in rate of interest
and costs associated with delays. Project cost estimates
increase by $1.5 million for each month delay on
major civil work.
At
present there are committed funds with identified
donors of $386.4 million. There is a funding gap
of almost $92 million mainly due to the departure
of the World Bank. ADB and JBIC are assisting HMG/Nepal
in pursuing alternative funding sources to replace
the credit which World Bank was to provide. According
to ADB sources, this gap will be likely be funded
partly by ADB and partly by other donors, possibly
Japan. Currently, Loans constitute 57.24%, Grants
15.96% and HMG/N 26.80% of funding for the project.
Recently proposed tariff changes are as follows:
Tariff
One
of the principal institutional reforms to be addressed
with the Melamchi Water Supply Project is the restructuring
of water tariffs. The Nepal Water Supply Corporation
(NWSC) has not been able to adequately recover its
operating costs due to a variety of factors including
extensive leakage in the system, lack of working
meters, a woefully inadequate billing system and
highly subsidized tariffs.
Ÿ By July 2004, the NWSC or the Water Utility Operator
(WUO) will introduce a new system of tariffs which
intends to start addressing systematic deficiencies
by recovering true operation costs. Tariff proposals
include the following:
Ÿ No change in the subsidized minimum volume of
10m3 (10,000 liters) per month for the first three
years, e.g. 2005-2007;
Ÿ No increase in the minimum volume charge of Rs.
50 per month for the first three years;
Ÿ A standard volumetric charge for metered residences
of Rs. 15 for 2005, Rs. 19 for 2006 and Rs. 23 for
2007 - the volumetric charge indicates water which
has been used in excess of the minimum volume;
Ÿ An increase in the basic un-metered tariff for
residential customers of Rs. 360 per month - this
charge is intended to motivate consumers to request
meters;
Ÿ Corresponding changes to the minimum charges and
un-metered tariffs for non- residential customers
and larger pipe sizes - the recommendation is for
a uniform volumetric tariff of Rs. 30m3 to be held
until the residential volumetric tariff catches
up;
Ÿ It is expected that both the residential minimum
volume tariff as well as the volumetric tariff will
increase after 2007;
Ÿ The minimum volume will eventually decrease as
service improvements are provided ultimately dropping
to 5m3;
Ÿ Standpipes to receive a bulk supply tariff of
70% of standard volumetric charge for one year after
which time communities will have to form water user
groups or rely upon franchisees to manage standpipes,
otherwise these sources of water will be shut down;
Ÿ As service improvements are made to specific sectors,
as defined by increased water pressure and water
delivered on a fixed schedule for at least eight
hours per day, tariff will be levied at 150% of
volumetric charge for basic service;
Ÿ The Government will have power to intervene to
limit tariff increases for reasons of national policy
but will be required to compensate the WUO and/or
the Management Contractor.
Connection
costs
Although water tariffs will inevitably go up to
reflect a cost-recovery approach to the management
of Kathmandu Valley's water supply system, connections
costs should go down. There is a pro-poor provision
in the proposed changes for connection costs, which
are significantly lower than current charges, and
which should allow for more low income families
to receive piped water from the central system.
The proposed revised charges for new connections
are as follows:
Ÿ A standard charge, not in excess of Rs. 2,000,
for any new connection up to 30 meters from the
main line. This charge will cover all costs other
than the cost of the meter and the customer deposit
which is currently Rs. 1000;
Ÿ The charge for connections of more than 30 meters
from the main line will be based on the standard
charge plus a per meter charge for the length of
the connection in excess of 30 meters but less than
50 meters from the main line. For connections of
more than 50 meters, consumers will be responsible
for the full cost of placing the connecting pipe.
The WUO will be responsible for making the connection
to the distribution network and the installation
of meters at the customers' premises;
Ÿ Payment of the connection charge can be made in
monthly installments over a period of one year;
Ÿ Beginning July 16, 2005 the WUO will require that
new customers pay an initial deposit of not more
than three months' consumption for 20m3 (20,000
liters) per month at the standard residential tariff
- this comes out to Rs. 600 based on the volumetric
tariff of Rs. 15m3 which has been proposed for 2005
and the minimum volume charge of Rs. 50;
Ÿ The creation of a Low Income Consumer Unit (LICU),
under the new Management Contractor, has been proposed
to deal with consumer complaints that might otherwise
not receive attention. By the end of 2005, the LICU
will review the issue of multiple connections per
house (such connections are currently not permitted
by NWSC) and possibly request the WUO to alter its
restrictions on the supply of water to multi- occupancy
houses.
Meters
An essential component of the tariff restructuring
plan is the installation of high quality meters
for all consumers in Kathmandu Valley. As part of
the Proposal for Adjusting Water Tariffs in Kathmandu,
the proposed details on meters are as follows:
Ÿ Meters will be made available on a rental basis
and the cost will be added to the tariff. The monthly
meter rental amount will not be more than 1.5% of
the list price of the meter;
Ÿ There will be a choice of meters including a displacement
meter which will cost about $20 to purchase and
a "smart meter" which will run approximately
$35;
Ÿ The WUO will publish a price list for such meters
including an allowance for up to a 10% mark-up on
the bulk procurement cost;
Ÿ Customers may purchase or rent either the displacement
or smart meter;
Ÿ The purchase cost of a meter may be paid in monthly
installments over a one year period.
Levy
A levy will be established for residents of 14 VDCs
in the Melamchi Valley which are affected by the
diversion of water to the Kathmandu Valley. A levy
has not yet been established but will likely entail
a fixed remuneration per cubic foot of water diverted.
Sewerage
Charge
There is no proposed change in the sewerage charge
which is currently set at 50% of a given household's
water consumption.